SPICER -- Construction is under way of a new $1 million cell at the Kandiyohi County landfill in rural Spicer.

Advertisement

This week crews began installing a thick plastic liner on the massive expansion that is 175 feet wide and 850 feet long.

When it is filled with ga-rbage, the cell will be at least 100 feet tall. Based on the current flow of about 35,000 tons of gar-bage that comes to the landfill each year, the new cell will be filled in three or four years, said Jeff Bredberg, director of Environmental Services for Kandiyohi County.

The process to build a new cell involved putting down two feet of compacted clay at the bottom of the cell. The high-density plastic liner, which is 60 mil thick, is laid on top of the clay.

Piping that will collect and transport leachate -- the liquid runoff from the garbage and rain -- will be installed on top of the plastic liner and covered with a foot of washed sand.

Before the end of the year at least 6 feet of garbage needs to be spread over the entire base of the cell, and then topped with a foot of soil, to provide frost protection for the clay, said Bredberg.

"There's still a lot of work to do," he said, adding that the public would be amazed to see the construction process and what the landfill cell looks like before it's filled with garbage.

Seeing the large empty cell next to an existing mountain of buried garbage also provides a stark image.

The cost to build a new landfill cell is not cheap, said Bredberg, adding that if more people recycled more items, the life of the landfill could be extended and fewer tax dollars would be needed to expand the facility.

If nothing changes, Bredberg said the county has enough space to keep burying garbage at the site for another 35 to 42 years.

Bredberg said groups that are interested in touring the landfill and the construction site should contact him at 320-231-6229.


Similar Articles

Kathy Krause of Willmar unloads her family’s household recycling into the bins at the Kandiyohi County Recycling Center in Willmar. (Tribune photo by Carolyn Lange)

Ridgewater College President Doug Allen presents the upcoming building improvements on Friday during a "Building Breaking" ceremony to celebrate the beginning of their $14 million remodeling project.

The West Central Tribune's April 10 edition with the headline "Oh, say it ain't snow" was featured Wednesday on The Weather Channel. We have posted a video clip with this ...

More from around the web: