Bids for one of Minnesota Department of Transportation District 8's largest single-season construction projects came in well over original estimates. MnDOT engineers are now reviewing the low bid to determine options for the reconstruction of state Highway 23 between Granite Falls and Cottonwood.

021520.Hwy23.WEB..jpg
We are part of The Trust Project.

WILLMAR — One of the largest single-season road reconstruction projects on the state highways managed by the District 8 office of the Minnesota Department of Transportation is poised to get underway this spring.

One problem: The low bid for the project came in at nearly 27 percent over the estimated cost for the project.

The District 8 office in Willmar estimated that the project to rebuild the 18-mile portion of Highway 23 from Granite Falls to Cottonwood would cost $29.3 million.

The low bid submitted by Duininck Inc. , of Prinsburg, and opened Feb. 7 totaled $37,173,294.34. Central Specialties , of Alexandria, submitted the only other bid for the project, at a total cost of $39,363,498.10.

MnDOT has not awarded a bid for the project at this time.

ADVERTISEMENT

MnDOT engineers are currently comparing the bid abstracts with the original estimates to determine where the differences in cost exist, said Susann Karnowski, assistant district engineer in MnDOT’s Willmar office.

Anytime bids come in much higher than estimates, MnDOT takes a deep look at the differences between the bids and original estimate, she said. She expects that process to be completed within a couple of weeks. It will help MnDOT determine options.

MnDOT is likely to award the project, but doing so means it will likely have to delay other construction work scheduled for this season. There is only so much money in the construction fund, Karnowski said.

She said that the District 8 construction budget usually ranges from $40 million to $45 million per year. This year, the district is able to allocate a total of $63 million for construction. While the work for this project is slated for one season, Karnowski said MnDOT is allocating funding from two fiscal years.

Highway 23 is an important interregional corridor for the district and handles a large volume of commercial traffic, Karnowski said. The roadway, originally opened in 1980, is at the point where it needs major work, she added.

The project calls for resurfacing the roadway with concrete. It also involves updating the intersection of Highways 23 and U.S. 212 in Granite Falls; the realignment of Highway 23 and Lyon County Road 9 in Cottonwood; construction at the intersection with Lyon County Road 10; and constructing four new left-turn lanes.

What To Read Next
Benson and Turner Foods will process cattle and hogs at Waubun, Minnesota, on the White Earth Reservation with the help of a USDA grant.
A recent $30,000 per acre land sale in Sioux County, Iowa, sends signals into the land market in North Dakota, South Dakota, Minnesota and even as far away as Indiana.
Cathy Hedlof brings more than 40 years of management and accounting experience to her new position with Conway, Deuth & Schmiesing.
The Certified Financial Planner Board of Standards grants the Certified Financial Planner credential.